A contractor agreeing to finish a work in 150 days, employed 75 men each working 8 ...

A contractor agreeing to finish a work in 150 days, employed 75 men each working 8 hours daily. After 90 days, only \(2 / 7\) of the work was completed. Increasing the number of men by and each one is working now for 10 hours daily, the work can be completed in time.

A. 75
B. 225
C. 150
D. 100
E. 175





STAY UPDATED
FOLLOW US ON :


AboutContact usBack to Top
...

Disclaimer
All Views, Names, Acronyms, Trademarks, Expressed on this website are those of their respective owners. Please note that www.schoolngr.com is not affiliated with any of the institutions featured in this website. It is always recommended to visit an institutions or sources official website for more information. In the same vein, all comments placed here do not represent the opinion of schoolngr.com


SCHOOLNGR - © 2020 - 2024 - Tayo Hammed | Terms Of Service | Copyright | Privacy Policy