It was calculated that 75 men could complete a piece of work in 20 days. When work was ...

It was calculated that 75 men could complete a piece of work in 20 days. When work was scheduled to commence, it was found necessary to send 25 men to another project. How much longer will it take to complete the work?

A. 35
B. 25
C. 30
D. 45
E. 50





STAY UPDATED
FOLLOW US ON :


AboutContact usBack to Top
...

Disclaimer
All Views, Names, Acronyms, Trademarks, Expressed on this website are those of their respective owners. Please note that www.schoolngr.com is not affiliated with any of the institutions featured in this website. It is always recommended to visit an institutions or sources official website for more information. In the same vein, all comments placed here do not represent the opinion of schoolngr.com